Emmi Schweiz AG – Pallet Lift Modernization

  • Writer: ApoyoStudio
    ApoyoStudio
  • Oct 7
  • 2 min read

Location: Emmen LU

Duration: 6 months (from planning to commissioning)

Scope: Modernization of the pallet lift of a production line, including hydraulics, controls, and conveyor technology


Modernized hydraulic unit and control cabinet of the pallet lift at Emmi Switzerland AG


Initial Situation

The existing hydraulic pallet lift at Emmi Schweiz AG’s Emmen plant had become outdated.


The challenge: The conveying capacity was around 48 pallets per hour — the target was at least 60 pallets per hour with a 1,500 kg load capacity.

In addition, the lift needed to be integrated into the existing conveyor system and control structure.



Planning & Materials

Together with Emmi, we developed a modernization concept that combines reliability, performance, and safety:

  • New hydraulic unit and lift cylinders for higher operational safety

  • New lift control card for more precise control and faster lifting cycles

  • Completely new control cabinet built to current standards (incl. interfaces to the main control system)

  • Modernized conveyor technology and sensors at load handling devices (LAM)

  • New load detection system with light curtains for safe pallet handling

  • Revised fire protection doors (lower & upper levels) with improved drive technology and safety sensors

  • New position limit switches and safety systems at every level



Implementation

  • Dismantling of the old control system and hydraulics

  • Installation of the new control cabinet, hydraulic unit, and lift cylinders

  • Integration of new sensors, conveyor technology, and operator elements

  • Training for operating and maintenance personnel on-site



Result

The result: a modernized pallet lift that sustainably improved material flow at the Emmen plant.

Over 70 pallets per hour – reliable and with reduced cycle times

Higher operational safety through new hydraulics and control system

Seamless integration into existing systems

Short commissioning time – upgrade completed within 2 weeks